CourierPostOnline front page South Jersey News Sports Entertainment Classifieds Jobs Cars Real Estate Shopping


Customer Service
· Subscribe Now
· Switch to EZ-Pay
· About Us

Today's Weather
[an error occurred while processing this directive]
Metro Editor
Donna Jenkins
News Sections
South Jersey News
World Report
Sports
Business
Living
Opinion
Varsity
Weekly Sections
Communities
New! Nuestra Comunidad
Senior Scoop
South Jersey Living
South Jersey Scene
Static for Teens
Technology
Volunteers
Women on the Run
[an error occurred while processing this directive]
Featured
In Our Community
Corrections
Dating
Gannett Foundation
In Memoriam
Lottery Results
Obituaries
Pets
Photo Galleries
New! Spot News Kids Korner
South Jersey Guide
Weddings, Engagements & Anniversaries
Thursday, August 11, 2005Past Issues - S | M | T | W | T | F | S
 
South Jersey

Wednesday, July 18, 2001
Toppled bridge nearly ready to be righted

AL SCHELL/Courier-Post
Workers check the structural integrity of the light rail bridge, which is listing at 45 dgrees on a barge in the Rancocas Creek in Riverside. The span may be in place by the end of next week.
Visit these related links:
  • SPECIAL REPORT - South Jersey Light Rail: Trouble Down the Line
  • NJ Transit

  • By RICHARD PEARSALL
    Courier-Post Staff
    RIVERSIDE

    A 550-ton rail bridge that keeled over on Rancocas Creek in April, forcing five workers to jump for safety onto a pier or into the chilly creek, is expected to be righted next Wednesday.

    Three huge winches are anchored to the ground on each side of the creek, poised to pull the 210-foot, arched span up from one side while restraining it from the other.

    The bridge and the barge it is attached to have been resting at a 45-degree angle against an abutment on the Riverside bank of Rancocas Creek since the April 6 accident.

    The steel structure is part of a 34-mile light rail project, due to be completed by Jan. 1, 2003, that will link Camden to Trenton.

    "We've been putting in additional temporary bracing to ensure the stability of the structure," said Walker Kimball, project director for the South Jersey Rail Group, which was hired by NJ Transit to build the line.

    A device called a slider will be attached to the bottom of the structure, which is mounted on a 500-ton barge, to keep the bottom from sliding out and crushing a nearby pier as the span is lifted.

    The contractors in April had nearly completed work on the bridge and were ready to float it into position when the barge suddenly listed and the bridge toppled over.

    None of the five workers was seriously injured.

    Kimball blamed the accident on faulty design, the bridge being top heavy for the barge on which it was erected.

    The federal Occupational Safety and Health Administration said its investigation may not be completed until the fall.

    The righting of the bridge, originally scheduled for early July, has been twice postponed.

    "We like to be optimistic and aggressive," Kimball said, " but when we see something that needs to be done - some additional stiffening modifications - we're going to do it. We'd rather err on the side of caution." Kimball said the righting project is very much on schedule.

    Rigging International, the California firm hired to right the bridge, has until the middle of August to complete the job.

    On Tuesday, orange-vested workers clambered over, under and around the mammoth span, making final preparations for the move.

    NJ Transit spokesman Charles Ingoglia said the process will begin Monday, with the stringing of cable from the the winches to the arch, and climax Wednesday, when they plan to "actually, physically right it."

    Wednesday's operation could take up to 12 hours, Kimball said.

    "A little like watching grass grow," said Ken Finertie, a Delanco resident who has been following the progress - and setbacks - of the bridge project.

    The project will be completed by the end of next week, when the span is floated into position across the Rancocas and lowered onto the piers that will support it.

    The accident will not cost taxpayers any additional money, Ingoglia said.

    "We have a $604 million contract with South Jersey Rail Group to design, build, operate and maintain the line," Ingoglia said. "That still holds."

    The additional costs will be absorbed by one or more of the contractors and subcontractors involved in erecting the bridge.

    Ingoglia noted the light rail project "has moved forward in every other respect."

    He said NJ Transit will not know for certain if there will be any delays until the bridge is righted and fully inspected for structural damage.

    The bridge has been under construction since last fall. It will replace a smaller swing bridge that was used for 95 years.



    Copyright 2005 Courier-Post. Use of this site signifies your agreement to the Terms of Service (updated December, 2002).
    For questions, comments, or problems
    contact us.

    The Courier-Post is a part of Gannett Co. Inc., parent company of USA Today.

    FIND A JOB
    FIND A CAR
    FIND A HOME
    CLASSIFIEDS
    Deals and Coupons
    Auto Deals
    Consumer Web Directory
    Coupons
    End of Month Values
    Customer Central
    Subscribe
    Customer Service
    About Us
    Contacts
    Advertise
    Courier-Post Store
    Jobs at the Courier-Post
    Jobs with Gannett